Ramakrishna Mission Ashrama Narendrapur - Book Bank
Ramakrishna Mission Ashrama Narendrapur - Book Bank
Project Brief: Provide educational assistance to the needy as well as meritorious students from rural and urban areas through Book Bank
Project Type: Resource Centers (description)
Primary Focus: other (description)
Supporting Chapter Contact:
Athens
Project Type: Resource Centers (description)
Primary Focus: other (description)
Secondary Focus: other
Area: RuralSupporting Chapter Contact:
Athens
Status: CURRENT
Project Steward: Abhyuday Mandal
Project Partner(s): Swami Shivabhavananda
Project Address: Ramakrishna Mission Ashrama Narendrapur - Book Bank
Ramakrishna Mission Ashrama
Narendrapur
P.O. Narendrapur, West Bengal 700103
Tel: 011 91 3324772201
Stewarding Chapter: Athens
Project Steward: Abhyuday Mandal
Project Partner(s): Swami Shivabhavananda
Project Address: Ramakrishna Mission Ashrama Narendrapur - Book Bank
Ramakrishna Mission Ashrama
Narendrapur
P.O. Narendrapur, West Bengal 700103
Tel: 011 91 3324772201
Stewarding Chapter: Athens
| Sep 2026 | Athens | USD 8366 |
| Sep 2025 | Athens | USD 7471 |
| Aug 2024 | Athens | USD 7236 |
| Sep 2023 | Athens | USD 7288 |
| Aug 2022 | Athens | USD 6357 |
| Nov 2021 | Athens | USD 6845 |
| Oct 2020 | Athens | USD 4109 |
| Oct 2019 | Athens | USD 4244 |
| Jul 2018 | Athens | USD 10356 |
| Nov 2017 | Athens | USD 4727 |
| Oct 2016 | Athens | USD 10647 |
| Oct 2015 | Athens | USD 3497 |
| Apr 2015 | Athens | USD 8071 |
| Oct 2014 | Athens | USD 4981 |
| Oct 2013 | Athens | USD 1008 |
| Nov 2012 | Athens | USD 1000 |
| Feb 2012 | Sheffield | GBP 2000 |
| Jan 2012 | Athens | USD 1000 |
| Feb 2011 | Athens | USD 1000 |
| Apr 2010 | Athens | USD 1000 |
| Mar 2010 | Athens | USD 14000 |
| Apr 2009 | Athens | USD 2500 |
| Jan 2009 | Athens | USD 1000 |
| Mar 2008 | Atlanta | USD 2000 |
| Dec 2007 | Athens | USD 1000 |
| Jul 2007 | Athens | USD 1000 |
Total = $122703
The funding includes purchasing of the books as well as administrative costs.
Sep 2026 Audit Report 2025-26
Aug 2026 Project Metrics 2026
Apr 2026 Budget 2026-27
Dec 2025 Site Visit 2025
Sep 2025 Audit Report 2024-25
Jun 2025 Project Metrics 2025
Jun 2025 Budget 2025-26
Dec 2024 Site Visit 2024
Aug 2024 Budget 2024-25
Sep 2023 Project Metrics 2023
Sep 2023 Virtual Site Visit 2023
Aug 2023 Budget_2023_24
Aug 2022 Budget 2022-23
Apr 2022 Audit Report 2021-22
Nov 2021 Site Visit 2021
Nov 2021 Virtual Site Visit 2021
Oct 2021 Budget_2021_22
Apr 2021 Audit Report 2020-21
Jul 2020 Budget_2020_21
Dec 2019 Site Visit 2019
Jun 2019 Budget_2019_20
Dec 2018 Site Visit 2018
Jun 2018 Budget_2018_19
Dec 2017 Site Visit 2017
Aug 2017 Budget_2017_18
Apr 2016 Budget_2016_17
Dec 2015 Site Visit 2015
Apr 2015 Proposal Budget 2015
Dec 2014 Site Visit 2014
Sep 2014 Budget_2015-2017
Dec 2013 Site Visit Dec 2013
Jan 2012 Budget 2012-2014
Dec 2011 Site Visit Dec 2011
Dec 2010 Site Visit
Mar 2009 Budget 08-09-10
Mar 2009 2008 Progress Report
Jul 2008 2008 Site visit report
Jan 2008 Jan 08 : Six month rogress report
Dec 2006 Site Visit Report Dec 06
Nov 2006 Proposal