Subject: Child Welfare  Project Construction

Dear Shouri,

Hope you have received yesterday's e-mail. I am eagerly waiting for your mail which will release me from my tension.

Now I am giving you in details the item wise amount needed to complete the portion constructed serviceable and the time limit so that you can raise funds and give us financial support to complete the portion of the building constructed.

Presently we have 2 small rooms for teachers and office, 3 classrooms, one very small store and spacious open-air place between the corridor and the rooms so that maximum number of children can be accommodated with the partial construction. We are planning to construct the toilet immediately.

Now the details:
Srl.No. ITEM Fund needed In terms of Dollars Time frame
A. Construction of toilet (up to roof concrete) Rs.76,900/ $1602.00 1st October to 20th October 2002
B. Plastering inside and outside (9000 sft.) Rs.74,000/- $1541.00 16th October to 15th November 2002
C. complete concealed electrical wiring Rs.75,000/- $1563.00 16th October to 15th November 2002
D. Flooring (2500 sft.) (Ordinary gray flooring) Rs.32,200/- $670.00 16th October to 15th November 2002
E. Fitting doors(10 doors), windows (14 windows) with local woods and Fans & Light Rs.84,000/- $1750.00 16th October to 15th November 2002
F. Grill with 2 collapsible gates Rs.49,000/- $1021.00 16th November to 16th December 2002
G. Plumbing and sanitation completing fitting Rs,65,000/- $1146.00 17th December to 31st December 2002
H. Construction of parapet wall Rs.35,100/- $732.00 17th December to 31st December 2002
I. White wash, doors and windows painting Rs.20,000/- $432.00 1st January to 15th January 2003

I think minimum Rs.30,000/- ($625.00) will be needed for contingent expenses for completing the work mentioned above.

I hope I have given the requirements after consulting with proper mason, electrician, plumber and carpenter. I have not included the fund which I will have to spent for installation charge which will be required to be paid to the state electricity board for electricity connection.

Love

Rekhadi